Project Overview
Securefence constructed approximately 2,500 square metres of crushed stone haul roads at the Leonardo solar farm, giving contractors reliable access to the switchboards and owner build areas for the full duration of the construction programme. The roads were built at the site entrances and split across the site to serve the working areas.
The Requirement
A solar farm under construction needs access before it needs anything else. Plant, deliveries and trades have to reach the switchboards and the build areas repeatedly over months, and on unmade ground that becomes impossible in poor weather.
The client needed permanent duration haul roads rather than temporary matting, built to take construction traffic for the length of the programme, positioned at the site entrances and running to the areas where the work was concentrated.
The Securefence Solution
Securefence scraped and prepared the ground along the agreed routes, then constructed approximately 2,500 square metres of crushed stone haul road.
The roads were laid at the site entrances and split across the site to reach the switchboards and the owner build areas, rather than following a single route, so that separate working areas could be served without traffic converging.
The roads were built to remain in place and in service for the duration of the project, which set the depth and the construction of the formation.
Project Challenges
Stone delivery was the main logistical challenge. A haul road of this area consumes a high volume of material, and the deliveries had to be scheduled into an open site with a single busy site manager coordinating everything and everyone.
Archaeology constrained the routes. Parts of the site could not be disturbed, so the road alignments had to be set to avoid the protected areas rather than taking the direct line.
The Result
Approximately 2,500 square metres of crushed stone haul road were delivered, giving every contractor on site dependable access to the switchboards and owner build areas for the whole construction programme, with the archaeological areas left undisturbed.
Project Facts
- Location: Leonardo solar farm
- Sector: Solar, civils
- Scope: Crushed stone haul road construction
- Area constructed: Approximately 2,500 sqm